Morris Cogeneration, LLC
8805 Tabler Road
Morris, IL 60450
Morris Cogeneration, LLC (“Morris”) is a 192-megawatt combined heat and power facility in Morris, Illinois acquired in a partnership between Ironclad Energy and Fengate Asset Management. The Morris Cogeneration facility began commercial operations in 1998 and uses General Electric (GE) technology, including three combustion turbines and a steam turbine. The steam and energy produced at the facility is sold to LyondellBasell for use at its Morris petrochemical plant and the PJM market.
|
![]() |
2301 N. Brazosport Blvd
OC-801
Freeport, TX 77541
A partnership between Ironclad Energy Management and Fengate Asset Management acquired Freeport Power Limited, a 440-megawatt combined heat and power facility in Freeport, Texas. Also known as Oyster Creek Cogen and Dow “Power 8”, the facility began commercial operations in 1994 and uses General Electric (GE) turbine technology, including three combustion turbine-generators and a steam turbine-generator. The steam and power produced by the facility are integrated into Dow’s Oyster Creek and Plant A complexes.
|
![]() |
Less than 30 days after purchasing the energy assets within EBP in late 2016, we broke ground on a new $75M natural gas powerhouse and plan to retire the old coal powerhouse in early 2018. The short answer is this project dramatically improves air emissions while lowering customer costs thereby making EBP even more attractive to new industrial tenants that are looking to expand their operations. A snapshot of our operations in Rochester, NY are:
Ironclad focused on optimizing all aspects of RED Rochester. Upon close, the team worked with the EPA to extend permitting requirements to allow for the construction of the $75M boiler house. Within 30 days of the acquisition, construction commenced and the old coal boilerhouse was replaced 18 months later. Following construction of the boilerhouse, Ironclad created an accretive project group who ultimately executed another40+ accretive projects to bring additional value. The team worked with their customers to restructure the Utility Service Agreements to achieve better alignment with customers allowing for all parties to succeed with growth. Working with the customers, the team brought in large new customers and helped existing customers expand to a point where new generation was needed. The team then developed and constructed a new cogeneration facility on-site allowing for additional growth into the future and significantly better efficiency.
Stonepeak acquired a 100% ownership interest in Canal 1&2 from a subsidiary of GenOn Energy, Inc. in June 2018. Canal 1 is a residual oil-filed unit that went into service in 1968 and Canal 2 dual-fuel unit that went into service in 1976, and together the units represent a total of 1,124 MW of oil and natural gas fired generating capacity. The Canal 1, 2 & 3 site is located in Sandwich, Massachusetts on the Cape Cod Canal.
Together with Canal 3, Canal 1 & 2 form the 2nd largest single-site fossil-fuel generation site in the region, allowing the Canal site to enjoy substantial economies of scale in the premier New England power market where existing resources benefit from higher on-peak and capacity prices relative to other regions and significant barriers to entry by new resources.
![]()
|
||||||||||||||||
|
Canal 3 is a 350 MW natural gas fired peaking facility developed by NRG Energy Inc. and later completed by Stonepeak Infrastructure Partners and Ironclad Energy Partners. The project is co-located with Canal 1 & 2 in Sandwich, MA and utilizes best-in-class GE 7HA.02 technology with fast-start capability (full load < 10 minutes), advance emissions controls, and dual-fuel flexibility. The project cost approximately $315 million to construct and was completed in 2019.
Canal 3 Summary: Ironclad Energy Management, LLC (“Ironclad”) was the Owners representative during construction of facility acting as liaison to construction management team, EPC contractor, and major OEM suppliers. Fully commercialized Canal 3 to become a participating generator within ISO NE.
In addition, Ironclad developed the bidding strategy with Canal 3 as well as Canal 1&2 and managed the 50+mm gallon onsite No. 6 Oil and ULSD storage facility.
|
![]() |
The Bucksport Generation Plant was aquired by Stonepeak Infrastructure Partners and is a 175 MW natural gas fired peaking facility utilizing GE 7FA.03 technology. The plant is located in Bucksport, ME at the site of the former Verso paper mill, is primarily used for peaking and grid balancing in ISO New England, and was sold to JERA Americas Inc. in 2022.
|
![]() |